Calvert - Bucks, Energy from Waste Plant

 

  • Client: DNO : WPD
  • Location: Calvert
  • Description: 33KV & Fibre Pilot Contestable Grid Connection & 33Kv Private switchgear
  • Duration: 24 weeks
  • Value: £2,340,000

Project involved the Design and Construction 33kv Electrical Substation to accommodate DNO Contestable Switch Board & 33kv Private Switchboard / Transformer to include G59 protection scheme.  There was also close interface with WPD as there was a requirement for major reinforcement works within the National Grid 132Kv Primary Sub -station with a requirement for  WPD to build a new 132/33Kv bay within the  East Claydon sub-station POC site. The Contestable Cabling involved a an underground installation of 8kms of 33kv distribution  & 24SM Fibre Pilot cabling to serve the new EFW generating 25MW.

RCD-Case-Study-Bucks-Schematic

 

 

Scheme was particularly challenging as the cable route went through a very sensitive country estate with livestock and stud horse management. It also involved a BAPA Network Rail Engineering agreement  in order to directional drill under a rail line that was also being proposed for the new HS2 link. DNO and Private switch gear was designed and installed into combined customer bespoke  substation.

Case-Study-Bucks

  • Design of Contestable & Private side  - 33kv substation for incoming cable route, to include for electrical calculations for cabling and switch gear sizing, showing calculated losses, design earthing arrangement and protection arrangement.
  • Design & Construction of a new combined DNO & Private approved substation & housing to include construction of concrete plinth to accommodate flood protection.
  • Contestable Installation & commissioning of 33Kv &24SM Fibre Pilot underground cables between Major National Grid point of connection and customer intake substation in the middle of a very busy and tight site.
  • Cable route installation involved very careful planning as the 8kms involved sensitive countryside estate areas and many types of ramblers and council footpaths / rights of ways, many tenant farmers livestock & fields and a major specialist horse stud farm
  • Weather conditions and planning of timings of route were critical to all 3rd parties and the countryside environment along the very long agricultural cable route.
  • Route involved a BAPA network rail engineering design for the installation of a directional drill under a  network rail line which needed to accommodate the new proposed HS2 line.
  • Contestable & Private Supply and Install o0  33kvV switchgear, suitable protection relays, test plugs, emergency trip button, Battery and Charger & Multicore cabling
  • Commissioning and testing to include for the provision of test reports, as laids & certificates.