Yardley Water Mains

 

  • Client: Yardley Water Mains
  • Location: Yardley, Birmingham
  • Description: 1200m of Water Mains Laying
  • Duration: 6 Weeks
  • Value: £170,000

Adopting Utility Water: Severn Trent

welcome-to-rcd

  • Finished in budget & 4 weeks early on clients' construction programme
  • Liaison with all Stakeholders and Local Authority
  • Major Water diversion for 2 parallel new mains size 315mm and 180mm pipeline for a new Tescos Multi - development site
  • Specialist contaminated pipe needed along route together with specialist fittings due bending radius requirements.
  • Working in difficult conditions with meticulous detail needed reexact positions of pipe depths and separation due to main road infrastructure not yet fully formed and with one of new water mains being close to new high pressure gas mains.